Up we go with the beam.

Two beams in and one waiting to be lifted into place.

  The steel beams seemed to get off to a slow start, but now they are moving right along. As of today, there are six beams up--two more to go. The plan is to have all of the beams in by Thursday (May 2nd). Once they are in, framing of the walls begin, as well as getting the roof back on. The hope is to have the walls framed by May 14th. Sometime next week, all of the scaffolding will be removed.

  Stay tuned to the blog as things move along.